The Irish High Court's decision in McGill Construction Ltd v Blue Whisp Ltd [2024] IEHC 205 stands as a significant reaffirmation of the statutory adjudication process under the Construction Contracts Act 2013. The case clarifies several procedural and jurisdictional issues, reinforcing the robust enforcement of adjudicators' decisions in...
Our Articles
Unlike under the Housing Grants, Construction and Regeneration Act (as amended) in the UK, the failure to issue a payment response does not necessarily mean the amount of the payment claim notice is deemed accepted.
Irish standard forms of building contract include an option for the parties to refer a dispute to conciliation.